8 men can finish a piece of work in 40 days if 2 more men join them the work will be completed in
Answers
Answered by
1
please type full question dude
Answered by
12
8 men complete in 40 days
1 man complete in 320 days
8+2 = 10 mans can complete in 320/10 = 32 days