Math, asked by anjalipant7254, 8 months ago

8 men can finish half of the work in 3days .If the remaining work is to be completed in 2days , then the number of additional men required are---

Answers

Answered by neetusingh7584
0

Step-by-step explanation:

24 men can complete a work in 16 days

1 man's 1 days' work

12 men's 1 day's work

18 women can complete the work in 32 days

1 woman's 1 days work

6 women's 1 day's work

(12 men's + 6 women's) 16 days' work

Remaining work

(12 men's + 6 women's) 2 days' work

Remaining work

work is done in 1 day by 1 man

work will be done in 2 days by men = 16 men