8 men can finish half of the work in 3days .If the remaining work is to be completed in 2days , then the number of additional men required are---
Answers
Answered by
0
Step-by-step explanation:
24 men can complete a work in 16 days
1 man's 1 days' work
12 men's 1 day's work
18 women can complete the work in 32 days
1 woman's 1 days work
6 women's 1 day's work
(12 men's + 6 women's) 16 days' work
Remaining work
(12 men's + 6 women's) 2 days' work
Remaining work
work is done in 1 day by 1 man
work will be done in 2 days by men = 16 men