8 men or 10 boys can do a work in 36 days. In how many days can 16 men and 5 boys do the same work?

Answers

Answered by dev2125it1087
0

Answer:

Step-by-step explanation:

Answered by AmoliAcharya
2

They will finish the work in 14 days and 2/5th of 15th day.i.e.,14 days 4 hours and 48 minutes.

8 men take 36 days to finish work.

=> 1 man take 8 × 36 = 288 days to finish it.

So the amount of work done by 1 man in a day = 1/288

=> Amount of work done by 16 men in a day = 16 × 1/288

= 1/18

10 boys take 36 days to finish work.

=> 1 boy take 10 × 36 = 360 days to finish it.

So the amount of work done by 1 boy in a day = 1/360

=> Amount of work done by 5 boys in a day = 5 × 1/360

= 1/72

Work done by 16 men and 5 boys in a day = 1/18 + 1/72

= 5/72

Hence they will take 14 days and 2/5th of 15th day to complete the work.i.e.,14 days 4 hours and 48 minutes.