8 men wording 9 hours a day can complete 2 units of work in 20 days. In how many days can 6 men woring 10 hours a
day to complete 3 unit of work?
Answers
Answered by
0
Step-by-step explanation:
hope it will help you ,again any queries you a share with me
Attachments:
Answered by
1
Answer:
36
Step-by-step explanation:
8×9×20/ 2 = 6 ×10 × x /3
72 = 6x/3 => x = 36days