8 men wording 9 hours a day can complete 2 units of work in 20 days. In how many days can 6 men woring 10 hours a
day to complete 3 unit of work?​

Answers

Answered by nakshatranaik
0

Step-by-step explanation:

hope it will help you ,again any queries you a share with me

Attachments:
Answered by TheLostMonk
1

Answer:

36

Step-by-step explanation:

8×9×20/ 2 = 6 ×10 × x /3

72 = 6x/3 => x = 36days