Math, asked by aliasgar4d123, 16 days ago

8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

Answers

Answered by Jairagavan
1

Answer:

here your answer

Step-by-step explanation:

search-icon-header

Search for questions & chapters

search-icon-image

Class 11

>>Applied Mathematics

>>Numerical Applications

>>Time and work

>>8 men working for 9 hours a day can comp

Question

Bookmark

8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

Medium

Solution

verified

Verified by Toppr

Correct option is D)

8 men working for 9 hours a day can complete a piece of work in 20 days

8 men working for 1 hour a day can complete the work in (20 x 9) days (Less hours, More days)

1 man working for 1 hour a day can complete the work in (20 x 9 x 8) days (Less men, more days)

1 man working for 10 hours a day can complete the work in (

10

20×9×8

) days

7 men working for 10 hours a day can complete the work in (

7×10

20×9×8

) days =

7

144

days = 20

7

4

days