8 person can do a work in 5 days. I how many days that work can be completed by 4 person??
Answers
Answered by
1
Plz mark it as a brainliest answer plz
Attachments:
Answered by
1
Answer:
Step-by-step explanation:
If number of men is changed n times, time will change by (1/n) times the initial time.
8n = 4
(1/n) = 8/4
(1/n) of 5 = 2 of 5 = 10 days
4 person can do the work in 10 days
Thank U : )