8. Six workers can plaster the exterior of a building in
5 hours. If the job is to be completed in only 3 hours
45 minutes, how many workers will be needed? slove please i will follow you
Answers
Answered by
0
Answer:
In 48 hrs, the wall is built by 15 workers
Thus, in 30 hrs, the wall will be built by
30
15×48
workers
=24 workers
Step-by-step explanation:
please mark as brilliant