Math, asked by sumeetandgaurab, 5 months ago

8. Twelve men can do a piece of work in 15 days.
How many men are required to complete a work
which is three and a half times the original work
in 10 days?
(a) 18
(b) 54
(c) 63
(d) 70​

Answers

Answered by shadowsabers03
52

Assume each person has the same efficiency.

At a constant time interval, as the no. of men increases the amount of work to be done also increases, i.e., both are directly proportional.

\longrightarrow m\propto w\quad\quad\dots(1)

The time needed to complete a constant amount of work decreases as the no. of men increases, i.e., both are inversely proportional.

\longrightarrow m\propto \dfrac{1}{t}\quad\quad\dots(2)

Combining (1) and (2), we get,

\longrightarrow m\propto \dfrac{w}{t}

\Longrightarrow\dfrac{mt}{w}=constant

\Longrightarrow\dfrac{m_1t_1}{w_1}=\dfrac{m_2t_2}{w_2}

\longrightarrow m_2=\dfrac{m_1t_1w_2}{w_1t_2}\quad\quad\dots(3)

Here 12 men can do a piece of work in 15 days.

  • m_1=12
  • t_1=15

The new work to be done is three and a half times the original work.

  • w_2=3\,\dfrac{1}{2}\ w_1
  • w_2=\dfrac{7w_1}{2}

We're asked to find out no. of men required to complete this work in 10 days.

  • t_2=10

From (3),

\longrightarrow m_2=\dfrac{12\times 15\times \dfrac{7w_1}{2}}{w_1\times10}

\longrightarrow\underline{\underline{m_2=63}}

Therefore, 63 men are required.

Answered by rishavpriyadarshi07
1

Answer:

option c) 63 mens is the correct a answer

Similar questions