8. Twelve men can do a piece of work in 15 days.
How many men are required to complete a work
which is three and a half times the original work
in 10 days?
(a) 18
(b) 54
(c) 63
(d) 70
Answers
Answered by
52
Assume each person has the same efficiency.
At a constant time interval, as the no. of men increases the amount of work to be done also increases, i.e., both are directly proportional.
The time needed to complete a constant amount of work decreases as the no. of men increases, i.e., both are inversely proportional.
Combining (1) and (2), we get,
Here 12 men can do a piece of work in 15 days.
The new work to be done is three and a half times the original work.
We're asked to find out no. of men required to complete this work in 10 days.
From (3),
Therefore, 63 men are required.
Answered by
1
Answer:
option c) 63 mens is the correct a answer
Similar questions