8 women and 12 man can together finish an embroidery work in 10 days. While 6 women and 8 man can together finish it in 14 days.find the time taken by 1 women to finish work and also that the time taken by 1 man alone

Answers

Answered by mithravindhayd
1

Step-by-step explanation:

1 day's work of 6 women and 8 men= 1/14 part of work. Hence, the time taken by one woman alone to finish the work = 140 days and one man alone to finish the work = 280 days. HOPE THIS WILL HELP YOU