8 workers can construct a wall in 6 days if 12 workers are engaged for the same work what would be the time required to complete the work
Answers
Answered by
2
8 workers take 6 days to construct a wall.
So 1 worker will take 8×6 = 48 days for the same.
So for 12 workers will take
48÷12 = 4 days to finish the work