8 workers can do a work in 40 days. In how many days will 20 workers do it.
Answers
Answered by
6
→Question:
8 workers can do a work in 40 days. In how many days will 20 workers do it?
→Solution:
Given:
8 workers↔40days
20 workers↔x days
⇔We have,Inverse Variation here.
ie,More the workers,less the days will be.
⇒So 8×40=20×x
⇒320=20x
⇒x=320÷20
⇒∴x=16days
∴If 8 workers can do a work in 40 days,20 workers will do it in 16 days.
⇔Extra Information:
⇒Direct variation: y varies directly with x (y=kx)
⇒Inverse variation: y varies inversely with y (k=xy)
Answered by
4
Hope it helps uh!!!!..