8 workers working 7 hours a day can build a wall in 18 days how many days will 12 workers take to build a similar wall working 6 hours(With solution PLZZ)​

Answers

Answered by sujeetgund
3

Answer:Answer is 14 days. see the attachment for explanation and mark me as brainliest plzz.  <marquee direction=up scrollamount=2><font color=blue>Keep Asking & Keep Growing  </font>

Attachments:
Answered by umarkhan495gmailcom
1

Answer:

so, the answer is :- 14 days

Step-by-step explanation:

1 day =7 hrs

18 days =126 hrs

workers=8. then time taken = 126 hrs

workers =12. then time taken=x

126×8=12x

Attachments: