80 workers dig in 64m long trench in 16 days. How long will it take 60 workers to dig an 18-metre long trench?
Answers
Answered by
0
Answer:
75-76days
Step-by-step explanation:
75-76days
First multiply 80 , 64 and 16
It gives 81,920
Then,
divide 81,920 by 60*18
Which gives answer between 75 and 76