Math, asked by sy517769, 1 month ago

84 majdur sadak ka ek takada 36 din me banate hai. bataiye kitane majdur aur lagaya jay ki sadak 21 dino me puri ho jayega.​

Answers

Answered by Prat123
0

Answer:

60

Step-by-step explanation:

it is a question of inverse variation

first we will get total labor(majdur)=let be z

Majdur(labor) 84. z

time(din) 36. 21

84x36= zx21

84X36/21=z

12x12=z

144=z

total labor(majdur) needed to complete work is 144

more people needed =total - 84

=144-84

=60

Ans 60 more workers are needed to complete the work