86. In statement of cost, realisation value of scrap is deducted from :
(A) Works Cost
(B) Cost of Production
(C) Office Cost
(D) Total Cost
Answers
Answered by
2
Answer:
A. work/Factory cost..
note: If it is from an abnormal event, it should be treated in Costing P&L.
keep learning....