Math, asked by ekarajsmakkar, 9 months ago

9. 15 workers can do a job in 24 days. How long
will 8 workers take to complete the job?​

Answers

Answered by TanmayKiranUrunkar
3

Answer:

this is inverse proportion

15 workers in 24 days

8 workers in x days

therefore 15×24=8×x

x=15×3

x=45