Math, asked by agrimsharma2, 1 month ago

9. A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A,B and C

together finish it in 18 days. In how many days will A alone complete the work?

In how many days will C alone complete the work?

In how many days will A and C to
gether complete the work?



HOPE IT IS HELPFUL FOR YOU !!!

AND don't forget to follow me as I will new questions every day​

Answers

Answered by aayushimishra201
0

Answer:

(A+B+C)'s 1 day's  work =  

18

1

​  

 

(A+B)'s 1 day's work =  

24

1

​  

 

(B+C)'s 1 day's work =  

36

1

​  

 

∴ (A+C)'s 1 day's work=(2×  

18

1

​  

)−(  

24

1

​  

+  

36

1

​  

)

⇒(  

9

1

​  

)−(  

72

3+2

​  

)

⇒(  

9

1

​  

−  

72

5

​  

)

⇒(  

72

8−5

​  

)

⇒  

72

3

​  

=  

24

1

​  

 

so A and C together will do the work in 24 days.

Step-by-step explanation:

Similar questions