9. A, B and C can do a piece of work in 15, 12 and 30 days, respectively. They started together,
but C left after 2 days. In what time will the remaining work be completed by A and B ?
Answers
Answered by
3
- Solved for you.
- Refer to the attachment for the answer.
- Ask doubt in comments section.
Attachments:
johnwick97:
wrong answer C is completing work in 30 days not 20 days
Answered by
3
Answer:
Time taken by A+ B to complete remaining work =38/9 days