Math, asked by aditya51204574, 1 year ago

9. A contractor employs 56 labourers to lay a
road. He agrees to get the work done in 15
days. But the authorities want the work to
be completed in 10 days. How many more
men should he employ?​

Answers

Answered by MrConfusion
7

Answer:

15days------------------------56labours

10days------------------------??

(15/10)*56=84labours

Answered by windyyork
13

28 more men he should employ.

Step-by-step explanation:

Since we have given that

Number of labourers to lay a road = 56

Number of days it requires = 15

If the number of days it required = 10

So, we need to find the number of labourers.

According to question, it becomes,

56\times 15=10\times x\\\\840=10x\\\\x=\dfrac{840}{10}\\\\x=84

Hence, 84-56 = 28 more men he should employ.