9. A contractor employs 56 labourers to lay a
road. He agrees to get the work done in 15
days. But the authorities want the work to
be completed in 10 days. How many more
men should he employ?
Answers
Answered by
7
Answer:
15days------------------------56labours
10days------------------------??
(15/10)*56=84labours
Answered by
13
28 more men he should employ.
Step-by-step explanation:
Since we have given that
Number of labourers to lay a road = 56
Number of days it requires = 15
If the number of days it required = 10
So, we need to find the number of labourers.
According to question, it becomes,
Hence, 84-56 = 28 more men he should employ.
# learn more:
A contractor undertook to dig a canal in 72 days. He employed 70 men to dig it. How many extra Men should he employ in order to complete the work in 56 days?
https://brainly.in/question/11852589
Similar questions
Computer Science,
6 months ago
World Languages,
6 months ago
Math,
6 months ago
Social Sciences,
1 year ago
Geography,
1 year ago
English,
1 year ago
English,
1 year ago