9. If 40 men can finish a piece of work in 60 days, in how many days will 75 men finish the
same work?
Answers
Answered by
5
If 40 men can finish a piece of work in 60 days, in how many days will 75 men finish the
same work?
Step-by-step explanation:
Given that 40 men finished the work in 60 days. So 75 men can complete the work in 2400/75 = 32 days.
Answered by
2
Answer:
By proportion method we have,
Step-by-step explanation:
40:75::x:60
x = 60*40/75
x = 32 days