9 men and 12 boys finish a job in 12 days,12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days
Answers
Answered by
20
9M + 12B ----- 12 days ...........(1)
12M + 12B ------- 10 days........(2)
10M + 10B -------?
108M + 144B = 120M +120B
24B = 12M => 1M = 2B............(3)
From (1) & (3)
18B + 12B = 30B ---- 12 days
20B + 10B = 30B -----? => 12 days.
Answered by
13
Answer: 10 men and 10 boys can finish the same work in 12 days.
Step-by-step explanation:
Since we have given that
9 men and 12 boys finish a job = 12 days
12 men and 12 boys finish a job = 10 days
We will use "Time and work ":
We need to find the number of days in which 10 men and 10 boys can finish the same work.
Hence, 10 men and 10 boys can finish the same work in 12 days.
Similar questions
Math,
9 months ago
Hindi,
9 months ago
Physics,
1 year ago
Accountancy,
1 year ago
Computer Science,
1 year ago
Physics,
1 year ago
Math,
1 year ago