9 men and 12 boys finish a job in 12 days 12 men and 12 boys finish into 10 days 10 men and boys shell finish it how many days

Answers

Answered by dsbisht449
1

Answer:

MARK ME AS BRAINILIEST.

Step-by-step explanation:

9M + 12B ----- 12 days ...(1)

12M + 12B ------- 10 days....(2)

10M + 10B -------?

108M + 144B = 120M +120B

24B = 12M => 1M = 2B...(3)

From (1) & (3)

18B + 12B = 30B ---- 12 days

20B + 10B = 30B -----? => 12 days.