9 men and 12 women working 7 asserting complete three fourth of a job in 4 days and the remaining part of the job is done by 12 men and 7 women in 2 days working 5 hours a day in how many days for the entire job be done by 6 men and 4 women working 8 hours a day

Answers

Answered by sprao534
1

Please see the attachment