Math, asked by mulu02, 1 year ago

9 men can complete a job in 15 days if a man works thrice as fast as a woman find the number of days taken by 15 women to complete the job​

Answers

Answered by AnjaliRoy00
17

Step-by-step explanation:

9 men = 15days

1 men = 15*9 = 135 days

rate:

1 men = 3 women

so, 1 women = 135 *3 = 405 days..

so, 15 women = 405/15 = 27 days


mulu02: your dp is crazy
Answered by sharonr
2

The number of days taken by 15 women to complete the job

Solution:

Given that,

9 men can complete a job in 15 days

Then,

1 men can complete the job in 9 \times 15 = 135\ days

Given that,

A man works thrice as fast as a woman

Therefore,

1 men = 3 women

Find in how many days, 1 women will complete the work

1\ women = 135 \times 3 = 405\ days

Find the number of days taken by 15 women to complete the job

15\ women = \frac{405}{15} = 27

Thus number of days taken by 15 women to complete the job is 27

Learn more about this topic

Three men can complete a job in 3 days working 3 hours a day in how many days can 9 men completed working 1 hour a day

https://brainly.in/question/7828195

7 men can complete a work in 12 days. They started the work and after 5 days two men left. In how many days will the work be completed by the remaining men?

https://brainly.in/question/6679445

Similar questions