9 men can do a work in 10days how many more man are needed to finish doublenthe work in 18 days
Answers
Answered by
2
Answer:
1
Step-by-step explanation:
9 men needs 10 days
so 1 man will need 90 days to do it.
Now for doing the double work one man will need 90 x 2 days
thus to do it in 18 days we need (90x2)/18 men = 10
acc to prob. we had 9 men already we need 10. ie 1 more man to do it..