9 men can do a work in 12 days working 4 hours a day. In how many days can 6 men do the same work, working 8 hours a day?
Answers
Answered by
0
Answer:
Answer: b. 9
Step-by-step explanation:
Let d be the number of days it took to complete the work if 6 men do the same work, working 8 hours a day
If M1 men can do the work in working H1 hours per day and M2 men can do the same work in working H2 hours per day, then
\begin{lgathered}{M_1H_1}={M_2H_2}\\\\\Rightarrow\ {9\times12\times4}=6\times8\times d\\\\\Rightarrow d=\frac{9\times12\times4}{48}\\\\\Rightarrow d=9\ days\end{lgathered}
M
1
H
1
=M
2
H
2
⇒ 9×12×4=6×8×d
⇒d=
48
9×12×4
⇒d=9 days