Math, asked by tamaranaharshavardha, 20 hours ago

9. P and Q together finish a work in 30 days. They worked for 20 days and then Q left. The remaining work was done by P alone in 15 days. In how many days P alone can finish the total work?

Answers

Answered by kaushikpradeep621
1

Step-by-step explanation:

P + Q)'s 10 day's work= (1/30) x 10 = 1/3

Remaining work = (1 -1/3) = 2/3

2/3 work is done by P in 20 days.

∴ Whole work is done by P in 20 x (3/2) = 30 days

Answered by 009kitty
2

Step-by-step explanation:

Time taken by P to complete the work = 14 days

Time taken by Q to complete the work = 21 days

Q left work after = 6 days

Formula used:

If P and Q can do a piece of work in x and y days, respectively. They start working together and after t days Q leaves the work, then

Time taken to finish whole work = (x/y) × (y - t)

Calculation:

Here, P = 14 days, Q = 21 days, t = 6 days

According to the formula

Time taken to finish whole work = (x/y) × (y - t)

⇒ (14/21) × (21 - 6)

⇒ (2/3) × 15

⇒ 10 days

∴ The time taken to complete the work is 10 days.

Total work = 42 (L.C.M)

Efficiency of P = 3

Efficiency of Q = 2

P and Q work together for 6 days = 6 × (3 + 2)

Work completed = 30

Remaining work = 42 - 30 

⇒ 12

Remaining work completed by P alone = 12/3

⇒ 4 days

Total time = 6 days + 4 days 

⇒ 10 days

∴ The time taken to complete the work is 10 days.

Mark me as brainliest plz

Similar questions