Math, asked by pawankumarmundotiya8, 1 month ago

9. P can do a piece of work in x days. He finished 1/6th of the whole work and then Q alone did the rest of the work in 15 days. If together they can finish half of the whole work in 45/8 days, then find the value of x?

P can do a work in X days. He finished 1/6 of the entire work and then Q alone finished the rest in 15 days. If together they can finish half of the work in 45/8 days, then find the value of

X? (RRB NTPC 2016)

(a) 90/11

(c) 42

(b) 30

(d) 32/8

UPSI 14 BOOKS COMBO EXAMPUR through OFFICIAL APP NOW 9873111552

Answers

Answered by honeygala
0

Answer:

a) 90/11

Step-by-step explanation:

take total units of work as 900 units.

if they take 45/8 days.. then each day they do 900/(45/8) = 160 units of work.

q alone did 5/6 (900) units in 15 days.. so per day he did 750/15 = 50 units of work.

so p did 160-50= 110 units of work.

therefor. x = 900/110 = 90/11

Answered by braner
0

Given:

P finished (1/6) part of the work in X days.

Q alone finished the remaining work in 15 days

They can finish half work together in 45/8 days

Concept used:

If A does 1 unit of work in n day

Then 1 day work done by A will be 1/n units

1/(A’s work) + 1/(B’s work) = 1/(total work together)

Calculation:

Time to complete the whole wok by P alone = X days

P complete (1/6) work

Remaining work = 1 – (1/6) = 5/6

Q complete (5/6) work in 15 day

Q complete work = 15/(5/6)

Q complete work = 18 days

(P + Q)’s half work complete in 45/8 days

(P + Q)’s complete work [(45/8) × 2] = 45/4 days

So,

(1/P’s work) + (1/Q’s work) = [1/(P + Q)’s work}

⇒ (1/X) + (1/18) = 1/(45/4)

⇒ 1/X = (4/45) – (1/18)

⇒ 1/X = (8 – 5)/90

⇒ 1/X = 3/90

⇒ 1/X = 1/30

⇒ X = 30

∴The value of X is 30.

Formula Used:

Total work = Efficiency × Days required to complete the work

M1.D1.T1.E1/W1.C1 = M2.D2.T2.E2/W2.C2

M is the number of working men

D is the total number of days

T is total hours of working days

E is the efficiency of working men

W is total work

C is the consumption of working men

Calculation:

(P + Q) completed 1/2 work in 45/8 days

Total work will get complete in = 45/8 × 2 = 45/4 days

P completes 1/6 work in X days.

Remaining work = 1 - 1/6 = 5/6 completed by Q in 15 days.

Now by using the formula,

⇒ (Q × 15)/5/6 = {(P + Q) × 45/4}/1

⇒ 4 × (18 × Q) = 45(P + Q)

⇒ 72 Q = 45(P + Q)

⇒ 8Q = 5(P + Q)

⇒ 3Q = 5P

Efficiency of P is 3 units/day

Efficiency of Q is 5 units/day

(P + Q) completed work in 45/4 days

⇒ Total work = 45/4 × (3 + 5) = 45/4 × 8 = 90 units

Days required to complete 90 units of work by P is,

⇒ Days = 90/3 = 30 days

∴ Time required to complete the work by P is 30 days.

I HOPE THIS HELPS YOU.

AND PLEASE MARK ME AS BRAINLIEST.

♥️♥️

Similar questions