9 people can complete the electric fitting in a building in 5 days. How many people are required to complete the electric fitting in 3 days? (Assume that each person works at the same rate.)
a) 7
b) 11
c) 15
d) 18

Answers

Answered by Pranjol52
0

Answer:

It takes 5 days for 9 people

it will take 1 day for 45 people

it will be completed in 3 days by 15 people

So answer is 15(c)