9 persons complete a project in 12 days. In how many days will 6 persons complete the same project?
Answers
Answered by
2
Answer:
Persons. Days
9. 12
6. ?
it is of inverse proportion
so. 12*9
6
= 18 days
Ans: 6 person can complete project in 18 days