9 workers took 16 days to complete pucca boundary wall of school . If number of workers will be 2 then in how many days wall can be prepared
Answers
Answered by
0
workers=9
days =1
w2 =2
D2 =?
w1d1=w2d2
9×16=2×@
9×16/2=@
@=72 days