90 men are enagged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off so that the work may be finished in time ?​

Answers

Answered by kingksshav
2

Answer:

Total quantum of work planned = 90 * 40 = 3600 units.

Work completed in 25 days = 90 * 25 = 2250 units

Balance work remaining = 2250/2 * 1= 1125 units.

No.of days remaining = 15

No.of men required to finish = 1125/15 = 75

Hence, 15 men can be allowed to go.