90 person can dig a well in 40 days. after they have worked for 10 days,how many more persons should be employed so as to complete the work in another 20 days?
it is in direct and inverse variation
Answers
Answered by
0
Total work to do =90x40=3600unit
Work done in 10 day =90x10=900 units
Work still to do =3600-900=2700 units
If 90 person do this work it will take 30 day but we want to complete it in 20 day
Then
90x30=personx20
person required=2700/20
=270/2
=135
Total person =135
More person came =135-90=45
This is ur ans hope it will help you
Work done in 10 day =90x10=900 units
Work still to do =3600-900=2700 units
If 90 person do this work it will take 30 day but we want to complete it in 20 day
Then
90x30=personx20
person required=2700/20
=270/2
=135
Total person =135
More person came =135-90=45
This is ur ans hope it will help you
Thaarukeshini:
yes
Answered by
0
45 is the correct answer