92. A can do a piece of work in 10 hours, while B can do the same work in 6 hours. B worked at it for 4 hours. How long will A take to finish the remaining work?
(a) 3 hours (b) 3 hours 20 minutes
(c) 3 hours 50 minutes (d) 5 hours
Answers
Answered by
2
Step-by-step explanation:
A's 1 hour's work =
4
1
(B+C)'s 1 hour's work =
3
1
(A+C)'s 1 hour's work =
2
1
∴C's 1 hour's work =
2
1
−
4
1
=
4
1
B's 1 hour's work =
3
1
−
4
1
=
12
1
Hence, B will complete the whole work in 12 days.