96 men were engaged for a project of constructing a railway track of the length of 18km in four weeks. After
one week it was observed that the work of 4km was completed. How many additional men should be engaged
for timely completion of the project?​

Answers

Answered by kajalamrita09
5

Answer:

8mens more needed

Step-by-step explanation:

hope it helps you

mark me as brainliest

please mark me as brainliest please

Answered by kaus444dasarwar
22

Answer:

16 additional men

Step-by-step explanation:

(96*1week)/4 =((96+x)*3)/14

x=16