96 men were engaged for a project of constructing a railway track of the length of 18km in four weeks. After
one week it was observed that the work of 4km was completed. How many additional men should be engaged
for timely completion of the project?
Answers
Answered by
5
Answer:
8mens more needed
Step-by-step explanation:
hope it helps you
mark me as brainliest
please mark me as brainliest please
Answered by
22
Answer:
16 additional men
Step-by-step explanation:
(96*1week)/4 =((96+x)*3)/14
x=16
Similar questions