96 men were engaged for a project of constructing a railway track of the length of 18km in four weeks. After
one week it was observed that the work of 4km was completed. How many additional men should be engaged
for timely completion of the project?
Answers
Answered by
26
Answer:
16 additional men
Step-by-step explanation:
Men km week
96 4 1
? 14 3
96×14/4×1/3
112 total men
112-96=16 men required