96 men were engaged for a project of constructing a railway track of the length of 18km in four weeks. After
one week it was observed that the work of 4km was completed. How many additional men should be engaged
for timely completion of the project?​

Answers

Answered by raypratibha977
26

Answer:

16 additional men

Step-by-step explanation:

Men km week

96 4 1

? 14 3

96×14/4×1/3

112 total men

112-96=16 men required