960 men can do a work in 35 days
How many
more men should join
so that the work can be finished in
28 days
Answers
Answered by
3
Answer :
240 men are needed.
It is given that,
- 960 men can do a work in ' 35 days '
We've to find the no. of men should join them in order to complete the task in 28 days.
Let the total no. of men needed be ' x '.
Now,
960/x = 35/28
⇒ x = 960 × 35/28
∴ x = 1200
1200 men can finish the work in 28 days.
Now,
Subtract 960 from 1200 in order to find the number of men required.
= 1200 - 960
= 240
Therefore,
240 men are needed.