A 4 m thick clay layer beneath a building is
overlain by a permeable stratum and is underlain
by an impervious rock. The coefficient of
consolidation of the clay was found to be 0.025
cm2/ minute. The final expected settlement for
the layer is 11 cm.
How much time will take for 70% of the total
settlement to take place?
b. Determine the time required for a settlement
of 3 cm to occur.
Compute the settlement that would occur in
2 years