Math, asked by shavazali8, 2 days ago

a 9) P and Q can do a work in 12 days. Q and R can do the same work in 16 days, and R and P can do it in 24 days. Find the time in which P, Q and R can finish the work together. a. 9(3/4) days b. 10 days c. 11(1/4) days d. 10(2/3) days​

Answers

Answered by shashijha0302
1

Answer:

D

Step-by-step explanation:

Take LCM OF 12, 16 AND 24. =48

LET TOTAL WORK EQUAL TO 48

P+W Eff = 48/12 = 4

Q+R eff = 48/16 = 3

R+S eff = 48/24 = 2

eff of P+Q+R = 4+3+2/2= 9/2

Req Days = 48/9/2= 96/9= 32/3= 10 2/3