a 96. If 3 men or 6 boys can do a piece of work in 16 days, in how many days can 12 men and 8 boys do the same piece of work?
a. 6 days
b. 4 days
c. 2 days
d. 3 days
WRONG ANSWER TO BE REPORTED❌️❌️❌️
NO SPAM❌️❌️❌️
RIGHT ANSWER TO BE THANKS.☺️☺️☺️☺️☺️☺️
GIVE FORMULA FOR BRAINLIEST ☑️✅️☑️
Answers
Answered by
0
Answer:
3 days
Step-by-step explanation:
3m = 6w
So 12m + 8w = 24w + 8w = 32w
Since 6 women can complete work in 16 days, 32 women can complete it in :
16 x 6/32 = 3 days.
Answered by
1
3 men =6 boys or 1 man =2 boys
6 men and 8 boys = (2×6+8) boys or 20 boys .
if 6 boys can do a job in 20 days
=20 boys can do a job in 6×20/20 =6 days
a.6 days