Math, asked by badhanharpreet2211, 19 days ago

(a) A contractor who fails to complete a building in a certain specified time, is compelled to pay Rs. 200 for the first day of extra time required and the penalty thereafter is increased by Rs. 25 every day. If he loses Rs. 9,450, for how many days did the contract delayed ?​

Answers

Answered by avinayannk
2

Answer:

21 days

Step-by-step explanation:

1 200

2 225

3 250

4 275

5 300

6 325

7 350

8 375

9 400

10 425

11 450

12 475

13 500

14 525

15 550

16 575

17 600

18 625

19 650

20 675

21 700 = 9,450