(a) A contractor who fails to complete a building in a certain specified time, is compelled to pay Rs. 200 for the first day of extra time required and the penalty thereafter is increased by Rs. 25 every day. If he loses Rs. 9,450, for how many days did the contract delayed ?
Answers
Answered by
2
Answer:
21 days
Step-by-step explanation:
1 200
2 225
3 250
4 275
5 300
6 325
7 350
8 375
9 400
10 425
11 450
12 475
13 500
14 525
15 550
16 575
17 600
18 625
19 650
20 675
21 700 = 9,450