A aand B can do a piece of work in 12 days B and C can do a piece of work in 15 days while C and A can do it in 20 days
(a) How long will they take working together to complete the work?
(b) How long will each of them takes working individually to complete the work

Answers

Answered by Mausam11
0
A+B=12days. ......1
B+C=15 days. ......2
C+A=20 days. .....3
adding 1 and 2 and 3 we get
A+B+C+A+B+C=(12+15+20)days
2(A+B+C)=47 days
A+B+C=47/2days
hence A, Band C together can do work in 23.5 days


ahana14: but ans is 10 days
Answered by Rakesh1211
3
A and B can do a work in 12 days
B and C can do a work in 15 days
C and A can do a work in 20 days

L.C.M of 12,15,20=60
so,total work of (A and B)+(B and C)+(C and A) is 60.

1 day work of A and B is =60/12=5 unit
1 day work of B and C is =60/15=4 unit
1 day work of C and A is =60/20=3 unit

(A and B,B and C,C and A) 1 day total work=A+B+B+C+C+A=2(A+B+C)=5+4+3
A+B+C=12/2=6

so,A+B+C=6,A+B=5,B+C=4,C+A=3
A=(A+B+C-B+C)=(6-4)=2
B=(A+B+C-C+A)=(6-3)=3
C=(C+A-A)=(3-2)=1

1. Question ans

together complete the work=60/6=10 days

2. Question ans

A can complete the work=60/2=30 days
B can complete the work=60/3=20 days
C can complete the work=60/1=60 days

ahana14: correct ans
yash853: mindblowing :-) :-)