Math, asked by gurucharan1619, 1 year ago

A abd b working together could mow a field in 28 days and with help of c they could mowed it in 21 days how would c takes by himself

Answers

Answered by rishidas13
9

Answer:

C WILL FINISH IT IN 84 DAYS

Answered by sharonr
5

C alone takes 84 days to complete the work

Solution:

Given that,

A and b working together could mow a field in 28 days

Therefore, part of work done in 1 day is:

\frac{1}{A} + \frac{1}{B} = \frac{1}{28}

With help of c they could mowed it in 21 days

Therefore,

\frac{1}{A} + \frac{1}{B} + \frac{1}{C} = \frac{1}{21}\\\\\\frac{1}{28} + \frac{1}{C} = \frac{1}{21}\\\\\ \frac{1}{C} = \frac{1}{21} - \frac{1}{28} \\\\ \frac{1}{C} = \frac{28-21}{21 \times 28}\\\\ \frac{1}{C} = \frac{7}{21 \times 28}\\\\ \frac{1}{C} = \frac{1}{84}\\\\C = 84\ days

Thus C alone takes 84 days to complete the work

Learn more:

A,B and C working together can plough a field in 24/5 days .A and C together can do it in 8 days .How long would B working alone take to plough the field?

https://brainly.in/question/7180652

A and B working alone,can finish a piece of work in 10days and 15 days respectively.if they work together,how much of the work can they finish in 1 day and how many days will they take to finish the work....

https://brainly.in/question/3156166

Similar questions