English, asked by navjotkaur38, 11 months ago

a alone can complete a work in 36 days .b is 2/3 as efficient as a and if 7/9 of the work is done by a and b together then the remaining work is completed by c alone in 24 days . in how many days all the three will complete the whole work by working together.l​

Answers

Answered by efimia
3

Answer:

18 days

Explanation:

A can complete the work in 36 days.

Portion of work A can do in one day = 1/36

B is 2/3 as efficient as A.

There B can complete the work in 36÷2/3= 54 days.

Portion of work But can do in one day=1/54.

C complete (1-7/9) part of work in 24 days.

C completed 2/9 part of work in 24 days.

Therfore C can complete the work in (24÷2/9) =108 days.

Therefore portion of work C can complete in one day=1/108.

Therefore A, Band C together can complete in one day=(1/36) +(1/54) +(1/108)

=(3+2+1) /108=6/108=1/18.

Therefore A, B and C together can complete the work in= 1÷(1/18) days = 18 days.