a alone can do a piece of work in 10 days and B alone can do it 15 days in how many days will A and B together

Answers

Answered by gouthamchowdary
3
I think the answer is 6 days .

I hope it helps you.

please mark as brainliest
Answered by SruthiMohan
0

A takes 10 days & takes 15 days. So, let the total work be LCM(10,15) = 30 Units

A -> 10 days = 3 Units/dayB -> 15 days = 2 Units/day

A + B = 5 Units/day

Thus, TOTAL TIME = 30units/5units = 6 days