A alone can do a piece of work in 12 days and B alone can do do the same work in 15 days. A works alone for 4 days.In how many days will A and B together finish the remaining work

Answers

Answered by divergent07
0
a + b will do the remaining work in 4 4/9 days ♥️♥️