A alone can do a piece of work in 12 days . B do the sane work alone in 15 days . In how many days they A and B do the same work together
Answers
Answer:
mark me as rainliest plz
Step-by-step explanation:
Consider eating 60 ( L.C.M of 12 and 15 - for easy canculation. You can assume any number) candies is the above said work.
A takes 12 days to eat 60 candies. ie, A eats 5 candies per day. Similarly, B eats 4 candies per day. Together they eat 9 candies per day.
They work together for 4 days. ie, 4 x 9 = 36 candies. Now 24 candies are left. These 24 candies have to be eaten by A only.
A eats 5 candies per day. So A will require 24/5 days to eat the remaining candies.
1st method:
A and B complete a work in = 15 days
One day's work of (A + B) = 115
B complete the work in = 20 days;
One day's work of B = 120
Then, A's one day's work
= 115−120 = 4−36 = 160
Thus, A can complete the work in = 60 days.
2nd method:
(A + B)'s one day's % work = 100/15 = 6.66%
B's one day's % work = 100/20 = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = 100/1.66 = 60 days to complete the work.
Mark as brainliest please.