A alone can do a piece of work in 16 days and B alone can do it in 12 days, A, B and C together can do it in 4 days, then in how many days will A alone finish it? (A) 46/5 (B) 47/5 (C) 48/5 (D) 10 fa
Answers
Answered by
0
Answer:
(c)
Step-by-step explanation:
A alone can complete the work in 16 days.
B alone can complete the work in 12 days
L.C.M of 16 abd 12 is 48 units
So A completes 3 units a day
B completes 4 units a day
And as given A,B and C together completes the work in 4 days. So they completes 12 units a day
So C completes 5 units a day
so C completes the work in 48/5 days.