A alone can do a piece of work in 35 days If B is 40% more efficient than A, then B will finish the work in how many days​

Answers

Answered by sharansai42
3

Kindly check the attachment...

Hope it helps...

please make brainliest...!

Attachments:
Answered by Tringa0
4

The B will finish the work in 14 days.

Step-by-step explanation:

Days in which A can do a piece of work = 35

Work done by A in day = \frac{1}{35}

Days in which B can do a piece of work =

Efficiency of B = 40% more than A = A + 0.4A = 1.4A

Work done by B in a day :

1.4\times \frac{1}{35}=0.4

Work done by B in day = 0.4=\frac{1}{25}

Days in which B can do a piece of work = 25

The B will finish the work in 25 days.