Math, asked by mvsivakarthi10, 10 months ago

a alone can do a piece of work in 35 days. if b is 40% more efficient than a, then b will finish the work in how many days​

Answers

Answered by 8754408238a
3

Answer:

25 days

Step-by-step explanation:

100 A = 35 days

100 B =  y days (1)

wkt,

     100 B = 140 A  [GIVEN] (2)

    ⇒ sub (2) in (1),

         we get,

         140 A =  y days

∴ 100 : 140 :: y : 35

⇒ y = (100 × 35) ÷ 140

y = 25 days